Overview

RSP supports research administrators and Principal Investigators (PIs) in the Colleges/Schools/Divisions (C/S/D) in meeting the financial reporting requirements of sponsored projects. At the end of the award, this includes ensuring that reporting is in accordance with sponsor terms and that final financial reports and invoices are submitted according to sponsor timelines.

During award closeout, RSP accountants use a risk-based approach that leverages financial system reporting, established approval workflows, and collaboration with campus. This approach enables timely closeout while focusing review efforts based on risk.

The guidance below outlines the timelines, responsibilities, and processes that support compliant and efficient award closeout. This closeout process is designed to:

  • Enhance financial stewardship
  • Ensure compliance with sponsor requirements
  • Submit final financial reports according to sponsor timelines
  • Minimize suspense transfers
  • Mitigate late cost transfers

Below is a graphic summarizing the closeout process.

Closeout Timeline
Guidance for Campus Research Administrators

Financial management and award closeout are shared responsibilities. Below is a table of roles and actions organized by C/S/D research administrator, PI, and RSP accountant.

Role Actions
C/S/D
Research
Administrator
  • Review award expenditures for allowability, allocability, and reasonableness
  • Ensure any travelers reimbursed from an award are identifiable and/or paid on the award
  • Ensure sponsor pre-approval is received prior to equipment procurement on awards including special condition
  • Review and approve purchase card requests
  • Change costing allocations in accordance with award end dates
  • Retain clear and complete documentation for all expenses
  • Initiate, review, and approve cost transfers and adjustments as soon as unallowable expenses are identified and no later than 30 days after the award end date
  • Review and approve final subaward invoices; coordinate with PIs to ensure timely final approval and certification
  • Collaborate with PI to submit non-technical reports (e.g., invention disclosure, property reports)
  • Complete Final Review Closeout Checklist for Departments/Divisions (see Resources section)
  • Respond to RSP computational emails. Certify that all allowable expenditures have posted and no additional charges are anticipated so that RSP may submit final FFR/FSR. (A computational email includes clear timelines and lists any unresolved deficits, overdrafts, potentially unallowable expenses, or other transactions that need department review or action.)
PI
  • Review financial activity throughout the project period and assist with resolution of questionable expenditures
  • Collaborate with C/S/D research administrators and/or RSP to ensure financial stewardship of award and compliance with terms and conditions
  • Review and approve subaward invoices
  • Collaborate with C/S/D research administrators to submit non-technical reports (e.g., invention disclosure, property reports)
  • Prepare and submit technical reports
  • Send computational emails for award closeout; communicate clear timelines for expense review and cost transfers
  • Conduct risk-based expense review based on enterprise financial system reporting
  • Provide expense review documentation to C/S/D according to closeout timelines (see graphic above)
RSP
Accountant
  • Collaborate with C/S/D for allowability review as needed
  • Review and approve C/S/D cost transfers and accounting adjustments
  • Confirm payment of final subaward invoice
  • Include C/S/D Deans offices on second computational email and initiate suspense transfers if needed
  • Prepare final account reconciliation for award closeout
  • Confirm obligations are $0
  • Generate consumption invoice, if needed, to prepare award for closeout
  • Prepare and submit final financial report and final invoice according to sponsor deadlines
Expense Review and Cost Transfers

Financial review is required throughout the life of the award, and costs should be transferred as needed during the lifecycle of the award and immediately following the end date. RSP accountants provide expense review documentation to campus no later than 60 days after the award end date for awards with a standard 120-day closeout schedule. The timelines described in the graphic above are designed to ensure final reports and invoices are submitted by sponsor-required due dates. For shorter closeout schedules, please work closely with your RSP accountant. A C/S/D final review checklist is available for C/S/D (see Resources section below).

RSP accountants follow established closeout timelines. Computational emails are sent by RSP to identify Suspense that require departmental action before final reporting. RSP accountants send two computational emails and one third computational email prior to initiating suspense transfers. Suspense accounts are utilized after three notifications have been sent. RSP accountants will engage the C/S/D Deans’ offices regarding which non-sponsored account to utilize according to the sequence described below.

Email/Step Timing Action
1st Computational Email Initial notification Sent to notify the department research admin of charges requiring review and action.
2nd Computational Email 10 calendar days after the first computational email Reminder notice. The corresponding Dean's Office is copied on the email.
3rd Computational Email 10 calendar days after the second computational email Final notice. The corresponding Dean's Office is copied and asked to confirm the suspense account to be used. A non-sponsored account may be substituted at the Deans Offices’ request.
Suspense Transfer 5 calendar days after the Third Computational Email RSP processes suspense transfers for any unallowable charges.

For PAAs required for closeout, RSP will engage Dean’s offices as needed for escalation.

Manual Journals and Accounting Adjustments

RSP accountants enter journals to support the management and closeout of awards. RSP-initiated journals include:

  • Residual balance transfers
  • Third party cost share (subaward and non-subaward)
  • Unrecovered F&A as cost share
  • Sponsor-to-sponsor cost share (infrequent)
  • Program income
  • F&A adjustments
  • Suspense transfers for non-salary costs if necessary

Campus research administrators initiate non-salary cost transfers and payroll accounting adjustments (PAAs).

RSP Review

Workday is a process-based system, and transactions flow through a series of approvals prior to posting to an award. Review and scrutiny are required at each step in the approval process. Final expense review is performed based on exception and risk.  RSP accountants conduct a targeted review focused on exceptions and risk indicators identified via available system reporting and tools. The exception-based review includes the following Workday reports and tools:

  • Award Budget to Actuals for Award Header (UW) report
  • Potentially Unallowable Expenses (UW) report
  • High Risk Transactions (UW) report
  • Awards with Cost Share (UW) report
  • Find Accounting Adjustments and Find Journals
  • F&A rate review
Subaward Closeout

Subaward contracts follow the terms of the prime sponsor and incorporate language requiring final invoices no later than 60 days after the subaward end date for awards. Automated emails are sent to sub-awardees on the end date of the award as a reminder for final invoice submission. These emails copy the C/S/D grant management specialists and UW departmental contacts.

RSP accountants follow up with the Outgoing Subawards Team and campus as needed to ensure payment of subaward final invoices. Delay in sub-awardee submission and approval of final subaward invoices will result in delays in award closeout.

Resources

If you have award closeout questions, please contact your RSP accountant. If you have questions or feedback regarding this webpage, please contact postaward@rsp.wisc.edu.